TASC enters worldwide service PDF Stampa E-mail
Scritto da Emanuele Banchi   
Mercoledì 01 Settembre 2010 13:36

by Bruce Watson
FRICS FACostE
UK delegate to the International Cost Engineering Council

Introduction

This paper was first presented to the International Cost Engineering Council on 24 July 2010 at the 7th International Cost Engineering World Congress in Singapore in a more condensed version than appears here.

The presentation was provided as an introduction to TASC which is short for The Assessment Service Centre for Vocational Qualifications for Project Controls in Industry. TASC offers a service to candidates in project control occupations to assess and evaluate their experience and capability as cost engineers, project managers, cost estimators and planning engineers.

Ultimo aggiornamento Mercoledì 01 Settembre 2010 16:39
Leggi tutto...
 
A comparative evaluation of decision making techniques PDF Stampa E-mail
Scritto da Massimiliano Arena   
Venerdì 30 Luglio 2010 20:17

(su questo articolo è pervenuto 1 commento - si veda sotto)

Classical approach and fuzzy set based model

This paper briefly recalls the basic steps in risk and uncertain conditions and describes a simple application of fuzzy set in a decision making (DM) development process, highlighting the main difference of the approaches. Taking into account that many management decisions have to be taken based on imprecise or even subjective determinations of preference constrains and goals, the condition of vagueness and indetermination may become of great interest and a relevant systematic model may be useful.

Ultimo aggiornamento Mercoledì 01 Settembre 2010 13:33
Leggi tutto...
 
La formazione nel campo dell'I.E. PDF Stampa E-mail
Scritto da Vittorio Borgia   
Venerdì 16 Aprile 2010 15:40

La gestione di un progetto o meglio del ciclo di vita di un progetto richiede conoscenze tecniche specifiche dipendenti dalla natura stessa del progetto e tutta una serie di cognizioni, conoscenze e competenze, che consentono in maniera matriciale una valutazione completa dei problemi connessi.

Premesso quanto sopra, occorre precisare che non necessariamente un progetto può essere gestito in maniera organica, infatti si può andare da una gestione a vista (esempio: costruisco una casa facendo le fondamenta le più robuste possibili e poi rizzo muri e pongo solai alla bisogna) ad una gestione razionale ed ottimale (esempio: costruisco una casa, richiedendo un progetto ad un professionista, rivolgendomi ad un costruttore con il quale stipulo un opportuno contratto, verificando in corso d’opera l’andamento dei lavori in quantità e qualità, controllando i tempi ed i costi, valutando tempestivamente eventuali varianti di progetto o di contratto, stipulando opportune assicurazioni etc.).

Ultimo aggiornamento Venerdì 16 Aprile 2010 16:13
Leggi tutto...
 
Economic crisis? Support organizations, promote Project Management PDF Stampa E-mail
Scritto da Panayotis Agrapidis   
Sabato 03 Aprile 2010 12:38

We must overcome a deep and painful crisis. Organizations have to decide how and when to cut expenses and if necessary reduce personnel. Even in this difficult environment we can increase Project Management adoption if we understand exactly Top Management needs and create an indispensable tool for them. To win this challenge we must involve personnel with proven experience in Project Management and adopt maximum flexibility in order to present innovative proposals and to apply Project Management tools and methodologies in a highly effective way. Our target must be to cover critical Organizations needs in a very short period of time. Producing results quickly and with low cost, will help us create the basis from where to start and step-by-step, with consecutive successes, increase the Organization’s Project Management orientation. We must pay attention not to abandon Project Management standards application, but apply them in a way to fulfill customer’s immediate needs.

Ultimo aggiornamento Sabato 03 Aprile 2010 13:44
Leggi tutto...
 
La Percentage of Completion come metrica di project control PDF Stampa E-mail
Scritto da Massimiliano Arena   
Sabato 27 Marzo 2010 15:02

(su questo articolo sono pervenuti 4 commenti - si veda sotto)

Nel presente articolo, si illustrano alcuni aspetti di fondo relativi al parametro PoC (Percentage of Completion), tipico delle metriche di project control, che trova applicazione in molti contesti di project management relativamente a progetti di durata pluriennale ed in particolare a quelli legati per contesto e tipologia di business ai principi contabili US-GAAP (United States Generally Accepted Accounting Principles); il PoC è anche un parametro largamente accettato nel mondo finanziario internazionale.

Come si mostrerà, vari metodi di calcolo del PoC, permettono una analisi comparata della misura dell’avanzamento del progetto.

Ultimo aggiornamento Mercoledì 01 Settembre 2010 13:31
Leggi tutto...
 
« InizioPrec.12Succ.Fine »

Pagina 1 di 2

Ultime News

TASC

Il tema della certificazione è sempre stato un ar...

Emanuele Banchi | 1.9.2010

Leggi tutto

International Conference on Construction Engineering and Project Management (ICCEPM-2011)

The Organizing Committee for the fourth Internatio...

Gianluca di Castri | 18.8.2010

Leggi tutto

I bilanci delle grandi imprese

Il n. 23 di Edilizia & Territorio pubbica i ri...

Gianluca di Castri | 18.6.2010

Leggi tutto

Ammissione alla FAST

Ho il piacere di informare i soci che, in data 25 ...

Gianluca di Castri | 26.5.2010

Leggi tutto

Assicurazione: comunicazione COLAP

In tutte le proposte di riforma delle professioni ...

Gianluca di Castri | 10.8.2009

Leggi tutto
AICE - Associazione Italiana di Ingegneria Economica, Powered by Joomla!